A closer look at what goes into your next home. Dated construction reports and photography from the AKHCON development in Abuja.

Explore the site records
Latest published report / 13th December 2025Select a photograph to explore

/ THE CONSTRUCTION ARCHIVE

Every stage.
On record.

Explore the dated reports and photographs, from structural work to finishing details. Each report describes work and plans at its publication date; contact our team for the latest site status.

December 2025 / 2 reports

ON SITE / ABUJA

SITE UPDATE / 2025

13th December

4 photographs

Internal plastering is over 85% complete. External plastering is 70% complete. All services first fix (mechanical and electrical) necessary before plastering are being installed, including conduit showers 🚿 and recessed tanks.

SITE UPDATE / 2025

7th December

3 photographs

Internal plastering is over 80% complete. External plastering is 50% complete. All services first fix (mechanical and electrical) necessary before plastering are being installed, including conduit showers 🚿 and recessed tanks.